TGOOD Modular 110kV prefabricated substation completed in harshest conditions on the planet.
TGOOD Global has completed a turnkey 110kV prefabricated substation in Kazakhstan during a freezing winter. TGOOD designed, manufactured, constructed and commissioned this 110kV substation of an 80MW solar farm within a record 5 months while being challenged with -50 degree temperatures.
This innovative substation solution was designed to ensure insulation properties and other operating requirements were met for a successful project outcome.

The project included:
- 110kV/20kV GIS modular substation solution
- Complete control, automation and DC systems
- 15 X 0.8kV/20kV 6.3MVA step-up prefabricated substations within the solar farm
- Complete design, manufacturer, civil work, installation and commissioning
This fast-tracked project was executed within 5 months from contract, including onsite commissioning. TGOOD’s prefabricated solution assisted in achieving this with onsite installation in Kazakhstan completed in less than 9 weeks.
Considering the harsh environment and frozen soil conditions onsite, TGOOD provided this two-level substation solution, which reduced the civil works scope by 50%. This reduced the overall footprint and complexity of the civil risks in the project.
TGOOD Global continues to work with customers around the world to provide flexible solutions that are best for project in record times.